I am trying to upgrade from ECC 6.0 EHP5 to EHP7 using SUM 1.0 SP8 tool but getting below error :
Conflicts found.
Check log file 'SPDA_CONFLCHK.LOG' for details.
To resolve the conflicts the current step will be repeated and you
must change your Add-on or Support Package selection or add
Conflict Resolution Patches (CRT)
Error in 'SPDA_CONFLCHK.LOG' :
2EETN219 The system found conflicts for add-on "LOCHRSAE" release "605" (see list):
3 ETN220 Support Package "SAPKE60460" of software component "SAP_HR" release "604"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60520INLOCHRSAE"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60518INLOCHRSAE"
3WETN230 Conflict resolution by including a CRT for "LOCHRSAE" release "605" and "SAPKE60460"
3 ETN220 Support Package "SAPKE60461" of software component "SAP_HR" release "604"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60520INLOCHRSAE"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60518INLOCHRSAE"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60512INLOCHRSAE"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60509INLOCHRSAE"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60508INLOCHRSAE"
3WETN230 Conflict resolution by including a CRT for "LOCHRSAE" release "605" and "SAPKE60461"
3 ETN220 Support Package "SAPKE60462" of software component "SAP_HR" release "604"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60520INLOCHRSAE"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60518INLOCHRSAE"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60512INLOCHRSAE"
4 ETN225 ... has conflicts with "LOCHRSAE" release "605" - piece list: "SAPK-60510INLOCHRSAE"
3WETN230 Conflict resolution by including a CRT for "LOCHRSAE" release "605" and "SAPKE60462"
1 ETN214X."**************************************************"
1 ETN251 End of phase: "'Conflict Check'"
1 ETN254 End date: "29.10.2013"
Already include this Support Packages to Path EPS/in
SAPK-60508INLOCHRSAE
SAPK-60509INLOCHRSAE
SAPK-605010INLOCHRSAE
SAPK-605012INLOCHRSAE
SAPK-605018INLOCHRSAE
SAPK-605020INLOCHRSAE
SAPKE60460
SAPKE60461
SAPKE60462
Then re-operation SUM tool but the conflicts still occurs.
Please find attached remaining log and guide me how can i resolve this issue