Hi,
Yes i know the same without network activities it can not be done.
But with network activities I am procuring material with Stock item as valuated project stock by assigning the material to internal activity.
We are not using external activity for material procurement as all accounting data are maintained in material master and not maintained manually which is required to be maintained in external activity.
how forecast calculation will happen ?
Also how project cash management will update the payment data ?
As for both SAP is suggesting that it will happen only for non stock item.
Regards,
Pradeep