Re: No order on weekly off from maint plan

$
0
0

Then create separate factory calendar with all days as working days & assign that in Maintenance plan.

 

As default, system has taken that factory calendar in which Sunday is week off as that factory calendar has been assigned to your plant.

 

Factory calendar can be assigned in different area.

 

  1. In Plant assignment
  2. In Work Center
  3. In Maintenance Plan
  4. In Maintenance Strategy (Factory calendar will be copied to strategy based plan)