Hi Dinesh,
The problem here is with planned order ,the time in routing will only come to picture whenever we convert planned order to production order but we are using basic date scheduling in MRP run so routing time should not effect the finish dates of planned order as for the schedule margin key we don;t have any floats before or after and in house production time in 2 days