Hi Gurus,
My requirement is to raise a event after the completion of LBWQ JOB which kicks off the process chain IN BW. Following is what i have done so far
1> Created a program Z_BW_RAISE_EVENT with variant which has BW system RFC destination and Event id as parameters.
2> I then copied the background job details from job controls and passed it to SM37. After that i included my program in the Step list as below
3. I then schedule the background job through job control as below.
what i want to do is schedule this v3 job on a daily basis and after the completion of this a event would be raised to start the delta infopack in BW.
4. As soon as save the settings in the scheduler and come back out of LBWe, these settings disappear along with my added program in the steps.
if i go back to LBWE , in JOB control, setting would have been gone. Undelying is the screenshot.
As you can see the system is telling the start date paramaters have not been maintained even though i maintained them in previous step and scheduled it to be a daily activity at a certain time. Also my abap program along with its variant also goes missing with this.
Is there anything im missing. Kindly advice. your help and advice would be higly appreciated.
Thanking you in advance
Regards
Rahul