Hi Dennis,
You can try the following process. It might help.
For Statutory requirement a time based maintenance plan can be created.
For Smoke Particle/ Noise, Mater Inspection Characteristics (MICs) can be created, with qualitative indicator.
Rest of the process might be mapped as below:-
1: Assign an Order to inspection type 14 in configuration.
2: Create Master Inspection Characteristics (Quantitative or Qualitative as per your requirement) and assign sampling procedure.
3: Create a task list with inspection point 300 and assign Master Inspection Characteristics to it. Assign control key PM01 (for internal) or PM03 (for external processing)
4: Create a Maintenance Plan with the same task list for an Equipment with the order type with inspection type 14
5: An Order will be created as per the schedule given in Maintenance Plan.
6: An inspection lot will be generated once the order is released.
7: Do result recording and usage decision for the same.
8: I think there is a provision to print certificate as well (I have not used it though)
Hope it will be useful.
Thanks and Regards,
Sanjay