Hi SAP Consultant,
Thanks for your reply.The problem is I am not getting the right results in avlb.check screen.
Below are the options that I have already tried (in line with your suggestion).
Locations used : Plant 1000 and plant 1100
Stock scenario as in original post
Option 1 :
Rule A : MISL rule linked to condition type X (with setting 'Switch off...')
Rule B : Normal location substitution rule linked to condition type Y
Rule C : Rule with 'Consolidation location' as plant 1000 linked to condition type Z
- All the above condition types the same access sequence
- condition type X (as step 10),Y(as step 20),Z(as step 30) assigned to same rule strategy
Result :
(Attaching the screenshots also if above not visible)
The result is as required for line item 20.
(5pcs of PROD1_07 from 1000 and PR for 11pcs of PROD1_07 from plant 1100 to 1000)
It doesn't work as required for line item 10.
(10 pcs of PROD1_05 from plant 1000 and 15 pcs PROD1_05 from plant 1100.No consolidation in plant 1000)
(this is not material specific)
Option 2 :
Rule A : MISL rule linked to condition type X (with setting 'Switch off...')
Rule C : Rule with 'Consolidation location' as plant 1000 linked to condition type Z
- All the above condition types the same access sequence
- condition type X (as step 10),Z(as step 20) assigned to same rule strategy
Result :
The result is as required for line item 20.
(5pcs of PROD1_07 sourced from 1000 and PR for 11pcs of PROD1_07 from plant 1100 to 1000)
Again,it doesn't work as required for line item 10 but behaves differently than option 1.
(Only PR for 15pcs of PROD1_05 from plant 1100 to 1000)
Am I missing something in the above ? Or needs a different approach ?
- Shankar
Message was edited by: Shankar Sundaramurthy