Hi Mariano,
Can you please help me out....
My situation is:
I am using planning strategy 40. Normally i will have next 6 months forecast plan (PIR:MD61) for my FERT item. For my FERT item, i have BOM components which has longer planned delivery time (40 days). But sometimes emergency sale order comes today & it needs to be delivered to customer within a week. How to handle these emergency situations? Will implementation of planning time fence help to handle this situation?
What is the difference between "Planned delivery time" & "Procurement lead time". Where to maintain "Procurement lead time" in material master?
Thanks