Hi
I have planned costs input in CJ40 against a WBS plan version "0" but when I run CJI4 no planned values are shown.
However if I run S_ALR_87013532 I can see the planned costs, why does CJI4 not show the costs?
thanks
Joe
Hi
I have planned costs input in CJ40 against a WBS plan version "0" but when I run CJI4 no planned values are shown.
However if I run S_ALR_87013532 I can see the planned costs, why does CJI4 not show the costs?
thanks
Joe