1. In DS Board -- we have DS strategy profile as SAP001 and PP strategy profile as SAP002 and we are running Heuristics like -- schedule sequence, remove backlog etc . These Heuristics have their own strategy settings related to scheduling mode and planning direction- how DS strategy profile or PP strategy profile influences the production planning and scheduling here ?
(a)Taking an example --In PP strategy profile(SAP002), the scheduling mode is -- 'infinite scheduling' while in case of DS strategy profile it is 'find slot'.Heuristic 'remove backlog' has scheduling mode as 'insert operation'. If I run heuristic 'remove backlog' in DS board then what scheduling mode will be chosen by system out of 3 -- Find slot, infinite and insert ?
(b)In case planning directions are different between PP strategy profile, DS strategy profile and the Heuristic being run --then which planning direction will be chosen ?
Thanks in advance for help.