Hi Ibrahim,
Go to MM02 - Workscheduling View -Click on Production Version. Pop screen appears -Enter the version number, Description Valid from, Valid to and click on Details.
Now another screen will Pop up. Here enter the Lot size from and lot size to.
Under Planning data - Detailed planning - Task List type select Master Recipe -Put F4 under group and search group number using material. System will display the group number -select the relevent group number.
Under Bill of Material -Alternative BOM put F4 and select the BOM
Now click on check-system will display another screen as task list and bom exists. Click on cancel X symbol - System will take back to previous screen and display task list and bom in green colour.
Click on continue, and again continue and SAVE
Version indicator will get selected on work scheduling view.
If you have multiple production versions and require to use only one production version then under basic data - Prod vers locked - if you maintain Locked for usage then that production version will not be used.
Thanks & Regards,
Ramagiri
.