Re: Process Controlled WF Decision Types

$
0
0

Hi Konstantin,

 

Thanks for the detailed explanation.

Ideally when a SC is approved at header level (using decision type 1) it is converted to a PO.

 

What happens in case of Decision Types 2, 3 and 4 if few line items of the SC are approved and others are rejected. Suppose line item 1 and 2 are approved and line items 3 and 4 are rejected.

 

Then is it the case that PO automatically gets created only for line items 1 and 2 only.

 

Thanks,

Sameer Tapre.